Shanghai DEMIKS Electric Power Technology Co.,LTD

Step-by-step process of substation construction

Views :
Update time : 2025-04-03

Constructing an electrical substation involves careful planning, engineering, and execution to ensure safety, reliability, and compliance with standards. Below is a detailed breakdown of the substation construction process, covering site selection, design, equipment installation, and commissioning.


1. Site Selection & Preparation

Key Considerations:

✔ Proximity to Load Centers – Minimizes transmission losses.
✔ Accessibility – Easy transport of heavy equipment (transformers, switchgear).
✔ Geotechnical & Environmental Factors – Stable soil, flood risk, seismic zone.
✔ Clearance & Safety – Adequate space for maintenance and future expansion.

Site Preparation Steps:

  • Land Clearing & Grading – Leveling the ground.

  • Soil Testing – Ensures foundation stability.

  • Fencing & Security – Prevents unauthorized access.


2. Substation Design & Layout

Types of Substations:

  • Air-Insulated Substation (AIS) – Outdoor, uses air as insulation.

  • Gas-Insulated Substation (GIS) – Compact, SF6 gas-insulated.

  • Hybrid Substation – Combination of AIS and GIS.

Key Design Components:

  1. Single-Line Diagram (SLD) – Shows electrical connections.

  2. Layout Plan – Positions transformers, switchgear, busbars, control room.

  3. Earthing System – Grounding grid for safety and fault current dissipation.

  4. Lightning Protection – Lightning masts/arresters.


3. Civil & Structural Work

A) Foundation Construction

  • Transformer Foundation – Reinforced concrete with oil containment.

  • Switchgear & Control Room – Concrete slab with cable trenches.

  • Gantry & Busbar Supports – Steel structures for overhead busbars.

B) Cable Trenches & Ducts

  • Underground conduits for power and control cables.

C) Drainage System

  • Prevents waterlogging (critical for oil-filled equipment).


4. Equipment Installation

A) Power Transformers

  • Transport & Placement – Heavy cranes required.

  • Oil Filling & Testing – Insulation resistance, turns ratio, DGA.

B) Switchgear (Circuit Breakers, Isolators, CT/PT)

  • HV Circuit Breakers (VCB, SF6, Oil).

  • Disconnectors (Isolators) – For maintenance isolation.

  • Current & Voltage Transformers (CT/PT) – For metering & protection.

C) Busbars & Conductors

  • Rigid Busbars (Aluminum/Copper) for indoor substations.

  • Strain Bus (Flexible conductors) for outdoor AIS.

D) Control & Protection Systems

  • Relay Panels (Overcurrent, differential, distance protection).

  • SCADA & Communication Systems – Remote monitoring.

E) Earthing & Lightning Protection

  • Grounding Grid – Copper/steel mesh buried underground.

  • Lightning Arresters – Rod gaps or surge arresters.


5. Cable Laying & Termination

  • Power Cables (XLPE, Oil-filled) – Terminated at bushings.

  • Control Cables – Connected to relay panels.

  • Testing – Insulation resistance, hi-pot, continuity.


6. Testing & Commissioning

Before energizing, perform:
✔ Insulation Resistance Test (Megger test).
✔ Transformer Turns Ratio (TTR) Test.
✔ Circuit Breaker Timing & Contact Resistance Test.
✔ Relay Calibration & Secondary Injection Test.
✔ Primary Injection Test (High-current testing).
✔ Polarity & Phase Sequence Check.


7. Energization & Handover

  • Gradual Voltage Application – First LV, then HV.

  • Load Testing – Verify performance under real conditions.

  • Documentation – As-built drawings, test reports, O&M manuals.


Key Standards for Substation Construction

  • IEC 61936 (Design & safety).

  • IEEE 80 (Grounding systems).

  • NFPA 70 (NEC) & IEC 62271 (Switchgear standards).


Challenges in Substation Construction

  • Heavy Equipment Logistics – Transporting large transformers.

  • Environmental Compliance – Oil spill prevention, noise control.

  • Grid Synchronization – Ensuring compatibility with existing networks.

The above content is published by demiks, please specify, demiks is a substation equipment manufacturer, specializing in the production of high-voltage tester, transformer tester, circuit breaker test equipment, relay tester, SF6 gas analyser, cable fault tester and other products, if you have power test testing needs, please feel free to contact demiks power science and technology limited company or send an email! Give us: contact@demikspower.com 

Related News
Read More >>
Relay Protection Testing and Commissioning Gu Relay Protection Testing and Commissioning Gu
04 .14.2025
Protection Relay Testing & Commissioning GuideProtection relays are critical for
how to test microwave transformer how to test microwave transformer
04 .14.2025
Testing a microwave oven transformer (MOT) requires caution because these transf
how to reset circuit breaker with test button how to reset circuit breaker with test button
04 .14.2025
Resetting a circuit breaker with a Test button (commonly found in GFCI or AFCI b
high voltage cable testing standards high voltage cable testing standards
04 .14.2025
High voltage cable testing standards are critical to ensure the safety, reliabil

Leave Your Message